Last reviewed November 2026. Sources are linked at the end of the page.
Do you need a permit to install a new residential driveway in California?
Usually not a building permit, but usually a street permit. The California Residential Code's list of work exempt from permits includes driveways and sidewalks no more than 30 inches above adjacent grade, and Murrieta repeats it in its IB-131 handout. Cities then control the part of the driveway in the public right-of-way through their own encroachment rules, which is where the permit comes in. In Murrieta that means the approach, the curb cut and the sidewalk crossing.
Which Murrieta permit covers which work
| Work | Permit | Office | Source |
|---|---|---|---|
| Driveway or walk on your lot | None, if no more than 30 in above adjacent grade, not over a basement and not an accessible route | Building and Safety, (951) 461-6062 | IB-131 |
| Patio slab on your lot | Not listed in IB-131; confirm before the pour | Building and Safety, (951) 461-6062 | IB-131 (not on the exempt list) |
| Approach, curb cut, curb, gutter or public sidewalk | Encroachment permit | Engineering Division, (951) 461-6077 | MMC 15.54.040 |
| New or wider driveway opening (RV access included) | Encroachment permit | Engineering Division | IB-164; MMC 15.54.040 |
| Fence over 6 ft, or a masonry or concrete wall | Building permit | Building and Safety | IB-131 |
| Retaining wall over 4 ft (footing to top) or with a surcharge | Building permit | Building and Safety | IB-131 |
| Patio cover; detached RV shade structure over 120 sq ft | Building permit | Building and Safety | IB-131 (not on the exempt list); IB-229 |
| Any digging | DigAlert ticket two working days ahead | 811 / DigAlert | Gov. Code 4216.2 |
Swipe sideways to see every column.
City of Murrieta IB-131 Permits Required (May 2024), IB-229 RV Access and Storage (November 2018), IB-164 Fact Sheet RV Structures (May 2024), Municipal Code 15.54.040; Government Code 4216.2. Read November 24, 2026.
The encroachment code is broad. Section 15.54.040 lists constructing or repairing "any curb, sidewalk, gutter ... drive approach, driveway, alley approach" within a public place, and separately bars entering or leaving a public place "at any location not approved and constructed as a driveway", which is why driving an RV over the curb is on the City's list of unlawful access.

Encroachment permit fees for a driveway, FY 2026/27
The City's Comprehensive User Fee Schedule for fiscal year 2026/27 sets the encroachment lines below. The City notes that fees are worked out on its Fee Calculation Form, so treat the sum as a planning figure, not a quote.
| Line | Fee |
|---|---|
| Encroachment permit | $106.33 |
| Facility indicator fee | $19.94 |
| Inspection, minimum 1 day per permit | $140.66 |
| Scope fee: driveway, residential | $382.12 |
| Fixed lines for a residential driveway, our sum | $649.05 |
| Curb and gutter, remove and replace | $1.66 per linear ft |
| Sidewalk, remove and replace | $1.66 per sq ft |
| Additional inspection days, residential or collector street | $44.30 per day |
| Overtime inspection | $210.44 per hour |
| Extension or renewal | 5% of the construction cost remaining |
City of Murrieta Comprehensive User Fee Schedule, Fiscal Year 2026/27, III. Engineering/Public Works, page 34. Permits are issued for a one-year construction period.
What the approach has to look like
Standard Drawing 308a
A residential approach in Murrieta is 12 to 30 feet wide, at least 6 inches of concrete on a subgrade compacted to 95 percent, with a 1 inch lip at the gutter, no more than a 2 percent cross slope where the sidewalk crosses and 20 feet of full-height curb between driveways on one frontage. The driveway approach page walks through the drawing line by line.
Where the driveway can go
- Apron edge at least 5 ft from the property line, hydrants, utility poles, signals and light standards (Development Code 16.34.080).
- 24 ft of clear back-out in front of a garage that faces the driveway (16.34.080).
- Nothing over 30 in tall in the traffic sight triangle at a driveway (16.34.080).
- At least 25% of the front yard kept landscaped in the single-family zones (16.28.070).
- Openings near an intersection placed per Standard Drawing 307, at least 5 ft from the curb return.
- Driveways over 150 ft to the house: 14 ft clear width and 10% grade or less, per the fire access guideline.

How the permit fits into the job
The usual order is HOA approval where the tract requires it, then the encroachment permit, then a DigAlert ticket at least two working days before digging, then the work and the City's inspection. The HOA approval guide covers the first step. The City's Building and Safety forms page gives 15 business days for permit processing at the moment, and its counters keep Monday to Friday, 8 to 5 hours at City Hall, 1 Town Square.
Next door: Wildomar and Riverside County
The same driveway over the line follows different paperwork. Wildomar charges $472 for a one-day non-development encroachment permit and lets only licensed contractors work under one; Riverside County, which covers French Valley and Winchester, charges $186 for a residential driveway approach. Details are on the Wildomar and French Valley pages.